CONSTRUCTION ENGINEERING & INSPECTION

CONSTRUCTION OF MANAGEMENT LANES, “DYNAMIC TOLL LANES” (DTL'S), ON THE LUIS A. FERRÉ HIGHWAY PR-52, PHASE I TO III SEVERAL UNITS

Inspection engineering services for the construction of lanes for the management of vehicular congestion, Dynamic Toll Lanes (DTL’s), Luis A. Ferré Highway PR-52. Five independent projects for the construction of lanes for the management of vehicular congestion San Juan, PR

Project AC-520130 – Construction Cost: $14,160,315.00

Construction of Congestion Management Lanes, “Dynamic Toll Lane” -DTL on Luis A. Ferré Highway PR-52, Phase I, Unit 1, from Station 98+20.00 to Station 123+00.00.  Includes construction of a two-lane reversible roadway on rigid concrete pavement (PCCP) and three bridges using AASHTO Type IV and V girders. The total length of all proposed bridges is 141.06 m and the total length of the proposed roadway is 2,339 m for a total project length of 2,480 m.

Project AC-520141 – Construction Cost: $12,907,535.00

Construction of Congestion Management Lanes, “Dynamic Toll Lane” – DTL on Luis A. Ferré Highway PR-52, Phase I, Unit 2, from Station 84+60.00 to Station 98+20.00. Includes construction of a two-lane reversible roadway on rigid concrete pavement (PCCP), and two bridges using AASHTO Type IV beams and box beams. The total length of all proposed bridges is 68 m and the total length of the proposed roadway is 1,292 m, for a total project length of 1,360 m.

Project AC-520142 – Construction Cost: $10,932,655.00

Construction of Congestion Management Lanes, “Dynamic Toll Lane” – DTL on Luis A. Ferré Highway PR-52, Phase I, Unit 3, from Station 63+00.00 to Station 84+60.00. Includes construction of a two-lane reversible roadway on rigid concrete pavement (PCCP) and two bridges using AASHTO Type IV girders. The total length of all proposed bridges is 63 m and the total length of the proposed roadway is 2,097 m, for a total project length of 2,160 m.

Project AC-520131 – Construction Cost: $18,956,788.00

Construction of Vehicular Congestion Management Lanes, “Dynamic Toll Lane” – DTL on Luis A. Ferré Highway PR-52, Phase II, Unit 1, from Station 30+80.00 to Station 63+00.00. Includes construction of a two-lane reversible roadway on rigid concrete pavement (PCCP) and two bridges using AASHTO Type IV and V girders.  The total length of all proposed bridges is 163 m and the total length of the proposed roadway is 3,057 m, for a total project length of 3,220 m.

Project AC-520143 – Construction Cost: $15,999,892.00

Construction of Congestion Management Lanes, “Dynamic Toll Lane” – DTL on Luis A. Ferré Highway PR-52, Phase II, Unit 2, from Station 15+00.00 (PR52DTL) to Station 30+80.00 (PR52DTL).  Includes construction of a two-lane reversible roadway on rigid concrete pavement (PCCP) and two bridges using AASHTO Type IV and V girders and prestressed box beams.  The total length of all proposed bridges is 125 m and the total length of the proposed roadway is 1,455 m, for a total project length of 1,580 m.

Client:

Puerto Rico Highway and Transportation Authority (PRHTA)

Services:

Management
Structures
Drainage
Pavement
Transportation Design
Inspection

Location:

San Juan, Puerto Rico

Year:

2021

Budget:

$6 Million